Project Overview:
Engineered and installed a new, larger propane system with only one day of service interruption to the 24/7 operations of the world’s second largest aluminum manufacturer
Upgraded propane system with four 30,000-gwc propane storage tanks and four vaporizers
• Relocated two old, failing 350-gph vaporizers and piping (in the way of two new tanks) to new location