College of the Holy Cross

Worcester, MA

Client:
College of the Holy Cross
Location:
Worcester, MA
Project:
Steam Line
Division:
Utility Construction
Architect:
Not Available
Design Engineer:
Oak Engineers
Construction Manager:
Not Available
Contract Value:
Not Available
Project Overview:

Installed approximately 600 feet of 10-inch steam line and a 4-inch condensate line, placed under drains in trench, and tied into existing drain system

One of the greatest testimonials to the quality of R.H. White’s work is the fact that we keep bringing them back – year in and year out.

We’ve had a positive working relationship with them for the twenty-plus years I’ve been at Holy Cross College. R.H. White delivers value while getting the job done.

If a problem ever arises, they respond immediately whether it’s on a weekend or in the middle of the night.

Scott MerrillDirector of Physical Plant – College of the Holy Cross